Cost Estimating In Construction

945 Words2 Pages

This chapter provides a review on the existing literature regarding uncertainty in cost estimating in construction. There is an examination of the definitions of terms, and a review surrounding the practice and forms of cost estimating. The review will also analyse the factors effecting cost uncertainty and its relative importance to construction projects before focusing on design information as a major proponent of the inherent uncertainty in estimating.
Key points have been identified within the literature and will be expanded upon in the following sections:
Cost Estimating
• Purpose of Cost Estimating
• Forms of Cost Estimating
• Importance of Cost Certainty
• Cost Estimating Performance in Construction
• Uncertainty
• Design Certainty
• Significance of Design on Cost Certainty
• Other factors affecting Cost Certainty
2.2 Cost Estimating

There are a variety of definitions of estimating within existing literature. The Oxford English dictionary (OED, 2013) defines an estimate as to“roughly calculate or judge the value, number, quantity, or extent of something.” This definition is very much in line with the Association of Project Management (APM) who defines an estimate as “An approximation of time and cost targets, refined throughout the life cycle.” They agree, but for the added dimension of ‘refinement throughout the lifecycle’ which is in cognizance of the construction industry’s use of estimating throughout the process, both preconstruction and construction.
Cost estimating within literature has found to have slightly different definitions. Ogunlana (1989) states that a cost estimate is there only to aid the future design of a project, this description contains little mention of the process used to get to that estimate....

... middle of paper ...

... set of assumptions to mitigate the effect of incomplete information at conceptual stage (Dell’Isola, 2003). As the project progresses the estimate will develop from being a ‘preliminary estimate’ to a ‘later stage estimate’ and the accuracy of the estimate is expected to improve (Ogunlana & Thorpe, 1991; Flyvberg et al, 2002; Jin et al, 2008).
2.4.2 Dual-Purpose Estimates

These estimates aim to determine the total costs and come into the wider field of cost planning. The use of this type of estimating would be brought about where a stringent requirement for cost control has been requested by the client. These estimates attempt to utilise ideas supported by Dysert (2006) that where uncertainty is present, a range of figures to represent the works rather than committing to a single point figure, would leave the client more informed about the scale of the project.

Open Document