Williams V Roffy Case Summary

725 Words2 Pages

The case was decided upon by judges Glidewell, Russell, and Purchas LJJ at the Court of Appeal of England and Wales. The plaintiff, Lester Williams, claimed against the defendants, Roffey Bros. and Nicholls (Contractors) Ltd., for the sum of £32,708.70. In the case of Williams and Roffey, Roffey Bros. were contracted by Shepherds Bush Housing Association to refurbish 27 flats in London. They sub-contracted Williams to do carpentry work for £20,000; however he was unable to complete the work as he ran into financial trouble. Roffey Bros. were going to be responsible under a penalty cause for late completion, so they promised to pay the plaintiffs a further £10,300, at a rate of £575 for each flat completed. Williams did eight flats and ceased work because he had only received £1,500, This caused Williams to subsequently sue for the additional sums in relation to the eight completed flats. New carpenters were brought in to complete the work and Williams claimed. It is argued that Roffey bros did not give consideration and the case was decided in his favour of Williams. This was due to the fact that Williams continued with the work, therefore did not breach his contract. …show more content…

Promises to perform existing obligations can now amount to consideration, even between contracting parties. Nevertheless, within these wider limits, consideration must still be found, as Russel LJ makes clear. The commercialistic approach of Roffey would sound the end of the road for consideration if it was adopted more widely. It gives rise to dischotomy between Roffey promises to pay more and a Re Selectmore/ Foakes v Beer/ Pinnel’s Case promise to pay less where you cannot use practical benefits. The differentiation is nigh on impossible to justify, consideration can mean two different things in two similar situations is clearly

More about Williams V Roffy Case Summary

Open Document