How Final Should Dispute Resolution Be

1533 Words4 Pages

HOW FINAL SHOULD

DISPUTE RESOLUTION BE?

Intro

The number of disputes in the construction industry is rising dramatically but it’s with the secondary disputes, or ‘disputes about disputes’, that this paper is concerned. While they have a professional and social purpose in ensuring that dispute resolution complies with the applicable rules, they naturally give rise to the question addressed in this paper: to what extent should challenges to the process or the result be allowed; or ‘How final should dispute resolution be?’ (Uff, 2010).

The first point to make is that the standard forms then in common use contained serious restrictions on what could become the subject of a formal dispute. For example, up to 1980, the JCT forms contained a conditional embargo on defects claims after the giving of the final certificate, an issue which led to at least two major House of Lords decisions before the bar was progressively lifted. After this incident there were, many secondary disputes as to whether defects claims could be pursued at all (Uff, 2010).

The requirement for an engineer’s decision as a condition precedent to the right to proceed to arbitration gave rise to a excess of decisions, both in the English courts and in a succession of published and unpublished arbitration awards on whether particular disputes had been properly seen to, so as to give the tribunal jurisdiction (Uff, 2010).

The Technology and Construction Court

Before 1996 the parties usually had a classic choice between arbitration or litigation. In both cases, as with the forms of contract, the general approach was that decisions were to be final, with only a few exceptions (Uff, 2010).

However, two exceptions were introduced. First, to avoid loss of bus...

... middle of paper ...

...h may not subsequently be challenged. In the modern world this cannot include decisions of third parties. It can include agreement things like time limits and prices (Uff, 2010).

In arbitration, while the procedure is subject to party autonomy, the right of challenge by appeal on a point of law is not, but this is subject to a major exception in that it is still possible to contract in to such an appeal — a provision that might be seen as increasingly out of touch. The bulk of commercial arbitration is subject to institutional rules (typically those of the London Court of international Arbitration or International Chamber of Commerce) which, on the contrary, exclude any appeal, thereby representing a different aspect of party autonomy (Uff, 2010).

Reference list

Uff, J., 2010. How Final Should Dispute Resolution Be?, s.l.: Society Of Construction Law.

Open Document